Why HIKS STAR exists

Every panel builder sells you a panel.
We sell you the end of three quiet failures.

Spend more than twenty years inside this industry and you stop being surprised by the same three moments. The panel that arrives looking finished and fails inspection on the details nobody photographed. The coordination study delivered as a PDF nobody applied, discovered only when a fault takes down the main incomer instead of one feeder. And the handover file so thin that two years later, at two in the morning, a facility engineer is standing in front of a tripped board with no settings record, no as-built and no phone number that answers.

None of these are dramatic failures. They are quiet ones. They cost programmes weeks, owners millions and engineers their sleep, and the industry has learned to treat them as normal.

HIKS STAR was founded in Dubai by engineers who have spent over twenty years on every side of this business - in the panel builder's workshop, on the contractor's programme, at the client's review table, and inside the OEM's product organisation. We have sat in every one of those seats, inherited every one of those failures, and know exactly what each side needs and never gets: the contractor needs a quotation that holds and a delivery date that is real; the consultant needs evidence, not assurances; the client needs an asset with a memory; the OEM needs its components applied the way they were engineered to be. This company was built so that the problem each side faces is finally resolved in one place.

Here, the person who quotes your panel is the engineer accountable for it. The study is done to protect your network rather than satisfy a submittal log. And the documentation is treated as part of the product, because when the panel is twenty years old, the documentation is the product.

We don't measure success at dispatch. We measure it at 2 a.m., ten years from now, when someone opens the door of our panel and finds everything they need.

That belief produces four commitments no other panel assembler in the Middle East puts in writing:

01Unique to HIKS STAR

The Panel Passport™

Every panel we build carries a QR code on its door linked to its complete digital build record, approved drawings, busbar torque records, stage photographs, FAT results, breaker settings and as-builts. Any engineer who ever stands in front of that panel, for the life of the asset, scans and has everything. No other assembler in the region hands over its work this way.

02Speed with substance

A technical quotation in 48 hours

Send a complete SLD and BOQ and an engineer, not a sales inbox, returns a priced, engineered quotation within two working days, including any risks we can already see in your design. We answer fast because the person answering doesn't need to ask anyone.

03Skin in the game

First-time approval, or the rework is on us

If a panel we build is rejected at consultant inspection for workmanship against the approved drawings and agreed standard, we correct it at our cost and on our programme risk. We can offer this because our internal inspection is harsher than yours.

04Engineer-to-engineer

The designer answers the phone

After handover you don't call a call centre. You call the engineer whose signature is on your FAT dossier, and because of the Panel Passport, whoever answers sees your panel's full history before you finish your first sentence.

We are deliberately founder-led and deliberately narrow: LV switchgear, power studies, automation and testing. Nothing else. Depth is the whole point, the GCC has enough companies that do everything adequately. It needed one that does this completely.

Quality, Standards & Verification

Quality here is not a certificate on a wall.
It is a sequence of hold points nobody can skip.

Every HIKS STAR assembly moves through a formal Inspection & Test Plan (ITP). Stages marked HOLD stop the build until inspection is passed and signed; stages marked WITNESS are open to your consultant or representative. Each signed stage, with its photographs, is filed into the panel's digital record, the same record the Panel Passport later exposes on the panel door.

StageActivity & acceptance basisPoint
ITP-1Document review, approved drawings, load schedule and project specification frozen; deviations closed before material order.HOLD
ITP-2Material receipt, breakers, busbar and components checked against BOM, ratings and OEM certificates; serials logged.HOLD
ITP-3Fabrication & chassis, enclosure dimensions, form-of-separation barriers, earth continuity of structure.WITNESS
ITP-4Busbar installation, clearances and creepage to IEC 61439 Table values; every joint torqued to OEM figures and torque-marked; records filed.HOLD
ITP-5Wiring & devices, point-to-point check against schematics; ferrule numbers verified; segregation of control and power.HOLD
ITP-6Pre-FAT internal inspection, full routine-verification dry run by an engineer who did not build the panel.HOLD
ITP-7Factory Acceptance Test, to the protocol agreed with your consultant; calibrated instruments with traceable certificates.WITNESS
ITP-8Packing & dispatch, protection, lifting provisions, document pack and Panel Passport QR affixed and verified live.WITNESS

Routine verification on every assembly
IEC 61439-1 Clause 11, no panel ships without all of it

  • Wiring, electrical operation and function checks against schematics
  • Insulation resistance and power-frequency dielectric test
  • Clearances and creepage distances
  • Protective-circuit continuity and effectiveness of earthing
  • Mechanical operation of doors, interlocks and withdrawable parts
  • Degree of protection (IP) of the enclosure
  • Devices, internal circuits and terminals per design documentation
  • Markings, labels and circuit schedule verification

Design basis
verified per project, stated in every quotation

  • Temperature rise, short-circuit withstand and dielectric properties established per IEC 61439-1 design-verification routes, declared against the OEM tested system
  • Derating assessed for GCC ambient (50 °C design where specified)
  • Protection settings from the project ETAP study, not catalogue defaults

What lands in your hands at handover

  1. As-built drawings, SLD, GA, schematics, terminations
  2. Complete FAT dossier with witnessed signatures
  3. Busbar torque records and stage photographs
  4. Breaker settings schedule (as commissioned)
  5. Component OEM certificates and serial log
  6. Routine verification records to IEC 61439-1
  7. Operation & maintenance manual
  8. Panel Passport™ QR, the above, permanently, on the panel door

If any item is missing, the panel has not been handed over. That is the standard.